Log Home Guys Blueprint
log prints
Log Home Guys Florida Cypress Log Home Erection
Log Home Construction From Start To Finish Shamrock Model
Florida Log Home Guys Shamrock Dry-in
Florida Cypress Log Home Dry-in by Log Home Guys
Florida Cypress Log Stack by Log Home Guys
florida cypress log home jobsite by Log Home Guys
Day 15
Day 15
Day 15
Day 15
September 22nd, Wednesday
Day 15 - Crew making good progress, stacking logs. Trash Dumpster delivered and jobsite cleaned.
September 23rd, Thursday
Day 16 - Crew close to having log wall stack complete. Well contractor onsite, drilled approximately 170 feet deep and installed 1.5 hp pump with tank.
Log Home Guys jobsite -Well Drilling
Log Home Guys- Well Complete Florida Cypress Log Home
Cypress Log Home Stack Construction by Log Home Guys
Cypress Dovetail Log Construction by Log Home Guys
Cypress Log Cabin Kit Sale by Log Home Guys
Day 16
Day 16
Day 16
Day 16
Day 16
September 24th, Friday
Day 17 - Crew continues log wall stack, installs decking on 12ft back covered porch. Built temporary stairs. Received interior framing package. Electric company onsite, set transformer and energized temporary electric pole.
Cypress Log Home Wall Stack by Log Home Guys
Day 17
September 25th, Saturday
Day 18 - Crew continues working on log stack.

September 26th, Sunday
Day 19 - No Work

September 27th, Monday
Day 20 -  Rained out.

September 28th, Tuesday
Day 21 -  Log walls complete, Interior Framing 50%.

Cypress Log Stack Day 18 By Log Home Guys of Florida
Florida Cypress log home interior framing by log Home Guys
Cypress Log Cabin Home Dry-in by Log Home Guys of Florida
Day 18
Day 21
Day 21
September 29th, Wednesday
Day 22 - Worked 1/2 day due to rain. Crew continues working on framing and starts roof support post.

September 30th, Thursday
Day 23 - Crew works on Structural Open Beam Roof System

Cypress Log Home Roof Construction by Log Home Guys of Florida
cypress log home for sale
florida log home for sale
Day 23
Day 23
Day 23
October 1st, Friday
Day 24 - Crew working on open beam roof system.

October 2nd, Saturday
Day 25 - Crew installed all rafters on Structural Open Beam Roof System

log home rafter set
October 3rd, Sunday
Day 26 -  No work.

October 4th, Monday
Day 27 - Crew working on full log gables ends.

October 5th, Tuesday
Day 28 - Crew finished full log gables.

cutting cypress gable logs
gable end full cypress logs
Day 25
Day 28
Day 28
Day 28
October 6th, Wednesday
Day 29 - Crew begins installing T&G roof covering. Electrician onsite coordinating wiring drops for ceiling areas and scheduled to be onsite to install on Monday.
og home open beam system
log home T&G
Day 29
Day 29
October 7th, Thursday
Day 30 - Crew finishes installing T&G roof covering.
cypress log home roof sheathing
October 8th, Friday
Day 31 - Crew  working on installing open beam roof purlin system.
cypress purlins on roof
October 9th, Saturday
Day 32 - Crew finishing open beam roof purlin system and working on open beam covered porches.

October 10th, Sunday - Day 33 - No work.

Day 30
Day 31
Day 31
log home under construction
Day 32
Copyright © 2014 Log Home Guys LLC.
[image of Log Home Guys Logo]
This page was last updated: March 25, 2016
This page gives great insight with complete details and descriptions for building a log home. This is a must see for anyone considering building a log home.
Day 15 to Day 33