October 29th, Friday
Day 51 - Crew working on log wall to roof transition, framing and siding. Electricians onsite. Metal roof crew onsite installing Galvalume 26 gauge metal roofing. Plumbers onsite.
Building department onsite for Framing, Electric, HVAC inspections and all were passed and signed off.
Gas company contractors onsite to go over scope of work. Cabinet contractor onsite double checking finished framing wall measurements and coordinating under cabinet lights and electric for range hood/microwave with electrician.
October 30th, Saturday
Day 52 - Crew working on roof to log transition, flashing and trimout of exterior doors and windows, bay window siding and fireplace cutout. Electricians onsite finished all work until trimout. Owner's onsite requested 4 double motion detector lights, one per corner and to add extra smoke detector to great room. Extra work completed. Owner's changed mind on Wood Floor, cancelled order and gave measurement sf. to owners to order new product. Fireplace contractor onsite and installed insert unit.
October 31th, Sunday
Day 53 - Stone crew onsite working.
November 1st, Monday
Day 54 - Crew finishing misc. items. Stone crew onsite working.
November 2nd, Tuesday
Day 55 - Crew finishing misc. items. Fireplace contractor onsite installing gas line connection. Stone crew onsite working and completed their scope of work. Metal roof crew back and finished bay window and completed their scope of work.
November 3nd, Wednesday
Day 56 - "Crew finished, Dry-in Complete". Insulation contractor onsite, drywall materials delivered.
November 4nd, Thursday
Day 57 - Insulation contractors onsite and completed interior insulation including the fire caulking. Delivered country sink and viewed kitchen cabinets at cabinet shop. Drywall contractor onsite.